No person shall commence work involving the operation of any tools, plant or equipment unless they have been trained, deemed competent and authorised. All operators shall read, understand and follow this safe work instruction

Description of work
Operation of a Bulldozer
Potential hazards
Exposed moving parts; combustion engine hazard with the potential to cause harm through entanglement, exposure to heat, dust, projectiles and sharp objects. Noise from engine; crush hazard; hydraulic ram; heated fluid; plant vs plant or plant vs pedestrian incident.
PPE required
Appropriate Footwear

1. PRE-Operation:

  • Prior to use a full Pre-start check shall be conducted including:
    • Fuel
    • Hydraulic oil
    • Engine oil
    • Transmission oil
    • Coolant - allow engine to cool before removing radiator cap.
    • Battery
    • Tracks - check tension and condition of cleats
    • Remove any mud lumps from sprockets
    • Check horn, reversing alarm, lights and instruments.
    • Test steering both ways
    • Check braking and park brake operation
    • Inspect tray for wear, damage, or loose or missing parts
    • Ensure that attachments are securely fitted, and safety pins or clips fitted
    • Inspect hoses and connections for splits, bulges, leaks or fractures and test hydraulic action of ram.
    • Check seat and in cabin for cleanliness and free of obstructions
    • Use hand holds to assist entry into and exit from driver's position.
    • Seat should be well-sprung and adjusted properly to allow operator to maintain a comfortable operating position.
    • Seat belt must be fitted, correctly adjusted and worn when LV is used
    • All gauges and dials must be clearly identified, within easy reach and be easily read.
    • Clean and adjust mirrors before commencing work, and if bumped
    • Safety equipment, including a DCP fire extinguisher, must be fitted to all mobile plant.

2. Operation

  • When pushing out a road, avoid pushing debris, for example stumps, trees, rocks and dirt, into standing timber. Do not create hang-ups. Lower chicots and hung-up frees as they are encountered along roadways.
  • Roads will be made to proper width, with sufficient turnarounds and turnouts.
  • Road will be kept free of hazards, for example, stumps, rocks and debris.
  • Keep well back from other working equipment when they are cutting roadways or stripping.

3. Winching - prior to winching, ensure the cable is in safe condition and the hook-up is secure.

  • Brakes will be applied and the blade will be lowered onto the ground during winching.
  • Winch only at the proper speed that the machine being winched is able to move. Winch in a straight line, not on angle.

4. Moving trailers - prior to hooking or unhooking any trailer, ensure the trailer is properly blocked (chocked).

  • Operators will be assisted in hooking up trailers.
  • While hooking or unhooking a trailer, ensure all personnel are clear of the area between the trailer and the bulldozer. While being assisted, ensure communications and directions are clear and understood before moving your machine.
  • Travel at proper speeds when pulling trailers.
  • Ensure that your bulldozer is capable of controlling the equipment/trailer being moved.
  • If moving a fuel trailer, ensure that it is hooked to a drawbar rather than on a winch.

5. Post Operation

  • Upon completion to tasks for the shift the operator is to ensure the following steps are completed:
  • Plant is refuelled and greased ready for next day's operation.
  • Tray is inspected and all residual material is scraped, washed or removed.
  • Any load dockets or logbooks are accurately completed and returned to the relevant supervisor or manager.
  • Plant is parked in safe secure manner and all keys are returned to key box or secured.