Client: Fremantle Ports

Location: Inner Harbour, North Quay, Fremantle , WA

 

Berth 8 & 9 Crane Rail Repairs

Scope of Work Summary:

  • Cut-out/breakout all delaminated, drummy, and loose concrete adjacent to each side of the existing crane rails
  • Cut and remove the damage sections of crane rail including any approved sub-base plate
  • Once all damaged concrete has been removed, clean back flaking and surface rust to the reinforced steel before coating with zinc rich primer
  • Use S50 10mm GP MCC460 W/C0.40 concrete with steel fibres (Dramix 3D 65/35BG) @ 20kg/M3. finishing with steel float then broom finish to ensure non-slip with no standing water.
  • Reinstate any existing asphalt and to be levelled to the existing R.L. and make good
  • Develop detailed environmental, safety and emergency management plans and frontline HSEQ documentation
  • Detailed site survey and set-out
  • Siteworks and vegetation clearing
  • Prepare and submit ASCON Drawings