Bridge 4908 Refurbishment over Wooroloo Brook

Bridge 4908 Refurbishment

Routine & Specific Maintenance to Bridge 4908, over Wooroloo Brook

nviro were awarded this tender to complete Bridge Maintenance Works to Bridge 4908 on Tilden Drive in Gidgegannup:

Project Description

Works included:

  • Excavation to 1500mm under bridge
  • Fabrication and installation of structural steel members.
  • Laying of new reinforcement, pouring of concrete in a remote location to strict specifications.
  • Installation of stormwater infrastructure
  • Preventative & Preservation Maintenance to jarrah timbers forming bridge substructure.

Structural steel Full & Half Cap replacement works were carried out during single lane closures with traffic management handled by Altus Traffic Management with all works undertaken in accordance with MRWA standards.